Carrickfergus Public Realm - Schedule of Works
15 February 2012
A schedule of works for the Carrickfergus Public Realm scheme is now available below:
High Street
Carriageway northside along High Street from Monument to Town Hall = 13/02/12 - 17/04/12
Footway northside along High Street from Monument to Town Hall = 17/04/12 - 22/06/12
Carriageway southside along High Street from Monument to Town Hall = 25/06/12 - 06/08/12
Footway southside along High Street from Monument to Town Hall = 07/08/12 - 25/09/12
Carriageway Surfacing along High Street from Monument to Town Hall = 26/09/12 - 28/09/12
Joymount
Next to High Street = 01/10/12 - 25/10/12
Next to Town Hall = 26/10/12 - 26/11/12
Carriageway Surfacing = 26/11/12 - 28/11/12/
Upper North Street
Phase 1 - Drainage Works = 29/02/12 - 30/03/12
Phase 2 - Footway Construction eastside = 02/04/12 - 16/05/12
Phase 3 - Footway Construction westside = 17/05/12 - 15/06/12
Phase 4 - Carriageway Construction central = 18/06/12 - 03/07/12
Lower North Street
Phase 1 - Drainage Works = 28/03/12 - 09/08/12
Phase 2 - Footway Construction eastside = 10/08/12 - 18/09/12
Phase 3 - Footway Construction westside = 19/09/12 - 25/10/12
Phase 4 - Carriageway Construction central = 26/10/12 - 09/11/12
Lancasterian Street
Resurfacing of Carriageway and Road Markings = 12/11/12 - 14/11/12
Market Place
Phase 1 - Retaining Wall Construction = 23/02/12 - 23/05/12
Phase 2a - Carriageway Construction Market Place Lower (next to Cuddys) = 24/05/12 - 06/07/12
Phase 2b - Carriageway Construction Market Place Upper (next to Action Cancer) = 06/07/12 - 22/08/12
Phase 3a - Footway Construction southside on Market Place Upper & Lower = 23/08/12 - 18/09/12
Phase 3b - Footway Construction northside on Market Place Upper & Lower = 19/09/12 - 19/10/12
West Street
Phase 1 - Drainage Works = 27/06/12 - 09/08/12
Phase 2 - Footway Construction Northside = 10/08/12 - 01/10/12
Phase 3 - Footway Construction Southside = 02/10/12 - 12/11/12
Phase 4 - Carrigeway Construction central = 13/11/12 - 03/12/12
Marine Highway
Phase 1 - Subway = 02/04/12 - 06/06/12
Phase 2 - Roadworks on Shoreside = 07/06/12 - 03/08/12
Phase 3 - Roadworks on Townside = 06/08/12 - 13/09/12
Castle Street
Phase 1 - Southside footway and carriageway = 12/06/12 -18/09/12
Phase 2 - Northside footway and carriageway = 09/09/12 - 19/11/12
Phase 3 - Carriageway Resurfacing = 19/11/12 - 22/11/12
New Puffin Crossing
Comissioning = 23/08/12 - 24/09/12
Removal of existing crossing = 26/10/12 - 31/10/12
This information should be used as a guide and may change on a monthly basis as revised programmes are submitted and any changes will be highlighted here. There may also be minor changes on site in which case the Amey Chartered Engineer will directly inform the traders affected.
For further information please contact:
Nicole Mulholland, Development Manager (Economic)
Telephone: 028 9336 6666
E-Mail: nicole.mulholland@carrickfergus.org